I. DATE: September 4, 2021 (Saturday)
TIME: 6:00AM – 6:00PM (12 Hours)
AFFECTED AREAS: Whole Coverage Areas of Calatrava and San Carlos Area
AFFECTED SUBSTATION: 20MVA San Carlos
REASON: To facilitate the activities of the National Grid Corporation of the Philippines (NGCP) .
NGCP ACTIVITY:
> Finalization of interconnection of Cadiz-San Carlos and Guihulngan 69kV line;
> Swingging of Cadiz 69kV line to new ABS switch of NGCP at San Carlos City;
> Interconnection of NGCP ABS switch to NONECO San Carlos Substation gantry;
NONECO RIDE-ON ACTIVITY:
> Replace two (2) rotten poles and 69kV structures at Toboso
II. DATE: September 4, 2021 (Saturday)
TIME: 6:00AM – 12:00NN (6 Hours)
AFFECTED AREAS: Whole Coverage Areas of Sagay, and Escalante, Portion of Cadiz City (Brgy. Tadlong, Brgy. VF Gustilo. Brgy. Magsaysay
AFFECTED SUBSTATION: 5MVA Lopez, 10MVA Sagay, 10MVA Escalante
NONECO RIDE-ON ACTIVITY:
> Replacement of leaning tower 69kV structure at Hacienda Paz, Brgy. Tinampa-an, Cadiz City.