NGCP SCHEDULED POWER INTERRUPTION ON MAY 8, 2021, AND MAY 9, 2021

As per letter request attached , the National Grid Corporation of the Philippines (NGCP) set scheduled Power Interruption to facilitate Preventive Maintenance Servicing (PMS) of its’ high voltage equipment on May 8, 2021 and May 9, 2021. The said scheduled interruption will affect NONECO’s Sub-transmission line along with the coops’ Ride-on activities as follows:

MAY 8, 2021 (Saturday)
AFFECTED SUB-TRANSMISSION:

Cadiz – Victorias 69Kv Sub- transmission line
AFFECTED AREAS:

Whole Coverage of EB Magalona, Victorias, Manapla, and
Portion of Cadiz (Sicaba, Cadiz Viejo, and portion of Caduhaan)

TIME: 6:00AM – 8:00AM (2Hours); 5:00PM -6:00PM (1Hour)

SUBSTATION AFFECTED:
15MVA Victorias Substation

AFFECTED FEEDERS:  EB Magalona, Victorias, and Portion of Manapla
Switching process will be conducted to facilitate the temporary shifting of power from Cadiz – Bacolod Substation.

TIME: 6:00AM -6:00PM (12Hours)

SUBSTATION AFFECTED:
5MVA IPI Manapla Substation

AFFECTED FEEDERS:
Manapla Proper, IPI Distillery, and Portion of Caduhaan

RIDE-ON ACTIVITIES OF NONECO: Facilitate the hotspot correction and Preventive Maintenance of high voltage equipment.

MAY 9, 2021 (Sunday)

AFFECTED SUB-TRANSMISSION:
Cadiz –San Carlos 69Kv Sub-transmission line , and Cadiz Tinampaan Sub-transmission line

AFFECTED AREAS:
Whole Coverage Areas of Cadiz, Sagay, Escalante, Toboso, Calatrava, San Carlos
TIME: 6:00AM – 6:00PM (12Hours)

SUBSTATION AFFECTED:
10MVA Cadiz, 5MVA Lopes, 10MVA Sagay, 10MVA Escalante,
and 20MVA San Carlos Substation
NONECO will conduct Ride-on Activity including replacement of rotten poles, and deteriorated structures of Sub-transmission lines, facilitate the hotspot correction, and Preventive Maintenance of high voltage equipment in all substations affected.

 